Audit completion
0 of 24 checks
0% verified
Check contractor credentials, payment protections, site quality controls and handover records before you sign or pay. Track verified evidence and review optional draft clauses with your project team.
Loading saved progress…
Audit completion
0 of 24 checks
0% verified
Critical clauses
0 / 17 verified
Keep high-risk evidence and agreement terms together.
Before signing or paying
Verify the evidence behind each check. Do not treat a checked box as legal, engineering, insurance or tax approval.
Contractor vetting & agreement
Mark a check verified only after reviewing its supporting records or confirming it with your adviser.
Verify the contractor or firm's legal name, PAN, GSTIN, registration status and relevant construction-service classification directly against current official records.
Evidence to collect
GST portal record and matching bank-account name
Risk if skipped: A mismatch or inactive registration can create tax, invoicing and recovery complications. Confirm your own tax treatment with a qualified tax professional.
Tip: Confirm the business address and bank beneficiary independently before making a payment.
Inspect an active site for safety and workmanship, then speak privately with an owner of a completed home about defects, delays and final costs.
Evidence to collect
Direct client references, including a home at least one year old
Risk if skipped: A portfolio can omit later defects, unresolved snags or extra-item disputes.
Tip: Ask whether final costs differed from the quote and whether defects appeared after the first monsoon.
Confirm the contractor and site lead can follow the project's approved structural drawings, reinforcement details, bar-bending schedules and architectural sections.
Evidence to collect
Engineer references and ability to read issued structural drawings
Risk if skipped: Misread reinforcement, cover or connection details can result in expensive rework and structural defects.
Tip: Ask the project structural engineer to review the contractor's proposed site team.
Ask a qualified insurance or labour-law professional to confirm the contractor's required worker coverage, policy period, insured parties and site details.
Evidence to collect
Current policy or coverage records checked for the project and workforce
Risk if skipped: A jobsite injury without appropriate coverage can expose workers and project parties to serious financial and legal consequences.
Agree who is responsible for daily coordination, inspection requests, material checks and keeping the client informed.
Evidence to collect
Named supervisor, qualifications and daily site-attendance record
Risk if skipped: An absent or frequently changing supervisor can leave workmanship and inspections uncoordinated.
Tip: Record the supervisor's name, phone number, working hours and escalation contact in the agreement.
With the contractor's consent, check references with local cement, steel and other material suppliers about reliability and delivery coordination.
Evidence to collect
Independent references from two material suppliers
Risk if skipped: Supply interruptions or payment disputes can delay a project and disrupt planned work.
Tie each payment to clearly defined, inspected work completed at site. Specify measurement, invoice review, approval and dispute steps; avoid paying for future work that has not been delivered.
Evidence to collect
Written stage schedule and joint measurement before each payment
Risk if skipped: Front-loaded payments can leave the owner exposed if progress stalls or the contractor leaves the project.
Agree the retention percentage, cap (if any), release date, inspection process and how notified defects will be addressed. The example in this checklist is 5% held for 12 months after handover.
Evidence to collect
Retention shown on every payment certificate and final account
Risk if skipped: Paying the full contract sum before defects are addressed may reduce the owner's leverage to secure agreed rectification.
Set a realistic completion date, define client-caused and other permitted extensions, require written notice, and have a lawyer review any daily liquidated-damages amount and cap.
Evidence to collect
Agreed baseline programme, completion date and written extension rules
Risk if skipped: Without clear dates and an agreed remedy, schedule slippage can be difficult and costly to resolve.
Attach the exact approved brands, grades, specifications and documentation for key materials. Require written approval before any substitution.
Evidence to collect
Signed brand matrix, product grades and delivery records
Risk if skipped: Generic descriptions such as 'good quality' may make it difficult to establish which products were agreed.
State whether rates are fixed, the period covered, which materials qualify for adjustment, the evidence required and how decreases are treated. Have the formula reviewed before signing.
Evidence to collect
Fixed-price period and documented adjustment formula
Risk if skipped: A vague escalation term can cause disputes or work stoppages over ordinary price changes.
Tip: The supplied example uses a 15% steel or cement trigger after a 12-month firm-price period; verify current market data and agree the formula in writing.
Define material breach, safety and workmanship remedies, cure periods, termination notice, handover of the site and valuation of completed work.
Evidence to collect
Written notice period, grounds, site-access and valuation procedure
Risk if skipped: Without a practical exit and measurement procedure, a failed contract can leave the site inaccessible and costs disputed.
Agree sampling frequency, specimen preparation, test ages, acceptance criteria and an appropriately qualified laboratory with the structural engineer. Follow the project specification and current applicable standards.
Evidence to collect
Pour register, sample IDs, chain of custody and lab reports
Risk if skipped: Without documented testing and traceability, concrete quality concerns are harder to investigate.
Ask the structural engineer and material supplier to specify the curing method and duration for each concrete and masonry element; record completion and interruptions.
Evidence to collect
Written curing method and dated site records
Risk if skipped: Inadequate or undocumented curing can compromise durability and cause avoidable cracking.
Tip: The supplied reference calls out 14–21 days for some work; follow the approved mix, specification and engineer's direction rather than applying one period to every material.
Coordinate electrical and plumbing routes before casting. Require written structural-engineer approval before any proposed cut or penetration in structural concrete.
Evidence to collect
Coordinated MEP drawings and approved sleeves before concrete pours
Risk if skipped: Unapproved cutting can damage reinforcement or reduce structural capacity.
Have the site engineer verify cover, spacer type, spacing, reinforcement position and formwork immediately before each pour using the approved drawings and specifications.
Evidence to collect
Pre-pour inspection record against engineer-approved cover details
Risk if skipped: Incorrect cover or displaced reinforcement can contribute to corrosion, cracking or reduced durability.
Tip: Use the cover dimensions specified by the structural drawings; they vary by member and exposure.
Specify whether subcontracting is permitted and require prior written approval for key structural or specialist work. Keep the primary contractor responsible for performance.
Evidence to collect
Named subcontractors, scope, qualifications and written consent
Risk if skipped: Unapproved changes in the executing team can reduce accountability and disrupt quality controls.
Agree a practical update schedule covering workforce, completed work, deliveries, inspections and issues requiring a decision.
Evidence to collect
Timestamped progress updates and a weekly work summary
Risk if skipped: Without regular records, delays and changes are harder to identify and resolve early.
Tip: Share location or personal data only with consent and through an agreed private project channel.
Specify the covered roof, wet areas, sumps and exterior interfaces, start date, response time, repair obligation, product warranties and exclusions. Have local counsel confirm suitable form and stamp requirements.
Evidence to collect
Signed warranty identifying covered areas, period, exclusions and claim process
Risk if skipped: A verbal promise may be difficult to enforce if leaks appear after handover.
Collect accurate service routes, junctions, cleanouts, sleeves and equipment locations before plastering or covering the work.
Evidence to collect
Marked-up drawings and dated photographs before concealment
Risk if skipped: Missing service records can make later maintenance or drilling unsafe and expensive.
Tip: Store a dated photo archive and a printed copy with the handover documents.
Schedule a joint walkthrough before handover. Record each defect, responsible party, target date and evidence of completion.
Evidence to collect
Room-by-room snag list with dated closure records
Risk if skipped: Unrecorded defects are easier to miss and harder to resolve after the work team demobilizes.
Tip: Check doors and windows, tile hollowness, paint finish, water pressure and drainage.
Include lawful debris disposal, safe removal of nails and offcuts, protection of neighboring property and return or reconciliation of owner-purchased surplus materials.
Evidence to collect
Written site-clearance and material/scrap handover record
Risk if skipped: Uncleared waste and disputed material balances can delay occupation and create avoidable costs.
Collect available warranty documents and test certificates for installed equipment, fixtures, switches, tanks and other specified products.
Evidence to collect
Original or verifiable invoices, serial numbers and product certificates
Risk if skipped: Missing invoices, serial numbers or installation records may complicate a manufacturer's warranty claim.
Release retention only according to the agreed contract after the defect-liability period, inspection and closure of notified defects.
Evidence to collect
Defect-liability expiry, joint inspection and signed release statement
Risk if skipped: Premature release can remove the agreed financial incentive to complete outstanding defect rectification.
Legal & commercial guidance
Use these as discussion points. Contract terms, statutory requirements and available remedies depend on the project and current law; have a Karnataka-qualified lawyer review the final agreement.
Release payment against measured and accepted physical progress, not the calendar alone.
Payment follows progressAgree the retention amount, defect-liability period, inspection and release process in writing.
12-month holdback exampleSet a realistic baseline, extension rules, notice procedure and lawyer-reviewed remedy.
Defined completion dateRecord approved brands and grades; require written approval and evidence for substitutions.
No vague substitutionsPlanning aid only, not legal, tax, insurance or engineering advice. References to standards, durations, rates, retention, warranties and remedies are examples to discuss with qualified professionals; they may not suit every project or be enforceable as written. Check applicable current requirements before relying on them.