Plumbing quality progress
0 of 22 checks
0% verified
Coordinate sleeves, concealed water lines, drainage, pressure testing, and rainwater harvesting before work is covered. Review project-specific details with the responsible professionals.
Loading saved progress…
Plumbing quality progress
0 of 22 checks
0% verified
Critical quality gates
0 / 15 verified
Do not plaster chases or close ceilings before the specified pipe tests are complete and documented.
Test pressure, duration, and acceptance criteria depend on the installed pipe system, manufacturer instructions, and approved project specification. The 10-bar / 24-hour figure in this checklist is a planning reference, not a universal test instruction. Have a qualified professional select and supervise the test; keep people clear of pressurized connections.
Interactive MEP tool
Verify an item after checking the relevant drawing, inspection, or test record with the responsible professional.
Coordinate and place pipe sleeves before concrete is poured. Do not cut, core-drill, or chip structural members without written approval from the structural engineer.
Standard / planning reference
Sleeve locations approved on coordinated structural and plumbing drawings
Evidence to collect: Approved sleeve layout and pre-pour site photographs
Risk if skipped: Unapproved openings can damage reinforcement or reduce the capacity of structural concrete.
Confirm the bathroom drop and drainage arrangement with the architect and structural engineer before casting; check the planned traps, pipe routes, waterproofing, and final floor build-up together.
Standard / planning reference
Depth coordinated with approved sections, trap dimensions, and finished floor levels
Evidence to collect: Recorded level measurements before the pour
Risk if skipped: Insufficient or inconsistent depth can force raised floors, awkward thresholds, or compromised drainage and waterproofing.
Locate roof outlets at the designed low points and coordinate sleeve clearance with columns, waterproofing details, and the pipe support arrangement.
Standard / planning reference
Sleeve position and roof drainage coordinated with structural drawings
Evidence to collect: Roof drainage layout and pre-pour photographs
Risk if skipped: Poorly placed outlets can obstruct pipe supports and create difficult-to-seal roof penetrations.
Confirm sink, dishwasher, and washing-machine locations with the kitchen and plumbing plans before placing slab sleeves.
Standard / planning reference
Sleeve positions coordinated with final cabinet and appliance layouts
Evidence to collect: Kitchen and utility service drawings checked before the pour
Risk if skipped: Missing or misplaced penetrations can lead to costly rework and damage to finished or waterproofed surfaces.
Check that the pipe material and pressure/temperature rating match the approved design and intended hot- and cold-water service. Do not substitute products without approval.
Standard / planning reference
Pipe class, pressure rating, and applicable standard confirmed by the plumbing designer
Evidence to collect: Product markings, invoices, and approved material submittal
Risk if skipped: An unsuitable pipe or unapproved substitution can fail under operating pressure or temperature.
Confirm each threaded fixture outlet uses a compatible fitting and is securely supported before the wall chase is closed.
Standard / planning reference
Compatible, securely fixed transition fittings approved for the selected pipe system
Evidence to collect: Outlet schedule and inspection photographs before concealment
Risk if skipped: Poorly supported or incompatible threaded connections can loosen or leak inside finished walls.
Ask the plumbing designer to review the supply layout and expected demand so commonly used outlets can operate as intended at the same time.
Standard / planning reference
Pipe sizing and routing designed for expected demand and available supply pressure
Evidence to collect: Plumbing layout and design review by the responsible professional
Risk if skipped: An inadequately designed supply layout may cause noticeable pressure changes when multiple fixtures are used.
Tip: Confirm the incoming supply, pump arrangement, and fixture schedule before pipe sizes are finalized.
Check that concealed pipework is supported and protected from movement, sharp edges, and contact with incompatible materials before it is covered.
Standard / planning reference
Support type and spacing follow the pipe-system manufacturer and approved installation details
Evidence to collect: Photographs of supports before plastering
Risk if skipped: Unsupported pipes can move, transmit noise, or place stress on joints.
Set the diverter position and orientation against the selected fixture instructions and final plaster/tile thickness.
Standard / planning reference
Fixture manufacturer dimensions coordinated with finished wall build-up
Evidence to collect: Level and depth check against the selected trim before closing the wall
Risk if skipped: Incorrect depth or alignment can prevent the trim from fitting and make the controls difficult to use.
Have the responsible plumber or engineer specify and supervise the test for the installed system. Keep concealed pipework accessible until the test passes and the result is documented.
Standard / planning reference
Test pressure, duration, and acceptance criteria set by the approved specification and pipe manufacturer
Evidence to collect: Dated test record showing readings, duration, gauge details, and responsible sign-off
Risk if skipped: Leaks discovered after plastering or ceiling closure are difficult and expensive to locate and repair.
Tip: The pasted reference suggests a 10-bar, 24-hour hold; confirm the correct test procedure and limits for the actual system with the responsible professional.
Use only purpose-made, pressure-rated temporary fittings installed by the person conducting the test. Keep people clear of pressurized connections.
Standard / planning reference
Temporary closures compatible with the pipe system and specified test pressure
Evidence to collect: Pre-test inspection of test caps and connections
Risk if skipped: Improvised or unrated closures can fail suddenly and cause injury or invalidate the test.
During the supervised test, inspect accessible joints for signs of leakage and have any issue repaired and retested before the pipework is concealed.
Standard / planning reference
Inspection method follows the approved test procedure
Evidence to collect: Recorded inspection of accessible joints and any corrective work
Risk if skipped: Small leaks can cause hidden dampness, damage finishes, and lead to repeat repairs.
Collect and review the test record before authorizing plastering or closing a false ceiling.
Standard / planning reference
Test record approved by the responsible plumbing professional
Evidence to collect: Signed test sheet with date, readings, test duration, and repair/retest notes
Risk if skipped: Without a record, it is difficult to establish that concealed pipework was tested and accepted before closure.
Verify WC soil lines, fixture waste lines, venting, and their final connections against the approved drainage design and local requirements.
Standard / planning reference
Separate routing, pipe sizes, and connections follow the approved plumbing and local authority design
Evidence to collect: Drainage riser diagram and pre-concealment inspection
Risk if skipped: Incorrect connections can cause odors, cross-flow, blockages, or non-compliant discharge.
Check the fall and direction of horizontal drains against the approved drawing before embedding them. Resolve any flat, back-falling, or unsupported sections.
Standard / planning reference
Gradient confirmed for pipe diameter and local plumbing design
Evidence to collect: Recorded level checks before the pipework is covered
Risk if skipped: Incorrect gradients can contribute to slow drainage, standing water, and recurring blockages.
Tip: The pasted reference uses 1:40 (25 mm per metre) as an example; have the designer confirm the required gradient for each run.
Confirm traps are correctly selected, installed, and vented for the fixtures and drainage arrangement.
Standard / planning reference
Trap type and water-seal depth meet the approved design and applicable requirements
Evidence to collect: Fixture and trap schedule checked before installation
Risk if skipped: A missing or ineffective trap seal can allow unpleasant sewer odors into occupied rooms.
Confirm cleanouts are provided where specified and remain accessible after cabinets, ceilings, and wall finishes are installed.
Standard / planning reference
Cleanout locations and access follow the approved drainage drawings
Evidence to collect: Cleanout locations visible and reachable after finishes
Risk if skipped: Inaccessible cleanouts can make routine inspection and clearing unnecessarily disruptive.
Verify vent-stack routing and termination with the plumbing designer, including clearances from openings and neighboring occupied spaces.
Standard / planning reference
Vent routing and termination comply with the approved design and local requirements
Evidence to collect: Vent-stack drawing and roof-level inspection
Risk if skipped: Poorly placed or omitted vents can contribute to trap-seal loss and nuisance odors.
Have the designer size the sump for the household's expected demand, available supply, and maintenance needs rather than relying on a generic rule of thumb.
Standard / planning reference
Capacity calculated from occupancy, supply reliability, demand, and local requirements
Evidence to collect: Documented capacity calculation and approved tank drawings
Risk if skipped: An undersized or poorly planned tank can disrupt supply; an oversized tank can waste space and allow water to remain stored too long.
Tip: The pasted reference gives 1,000–1,200 L per occupant as an example only; confirm actual capacity with the project designer.
Specify a compatible tank waterproofing system and confirm that any interior coating is certified for contact with drinking water.
Standard / planning reference
Waterproofing and any coating certified as suitable for potable-water contact
Evidence to collect: Product certification, application records, and inspection before filling
Risk if skipped: Unsuitable coatings or poor waterproofing can contaminate stored water or allow leakage into surrounding structures.
Ask the pump supplier or plumbing designer to confirm the required non-return and isolation valves for the installed system.
Standard / planning reference
Valve selection and locations checked against pump and system design
Evidence to collect: Pump schematic and commissioning record
Risk if skipped: Incorrect or missing valves can contribute to backflow, water hammer, or pump-system problems.
Confirm the roof runoff route, first-flush arrangement, filtration, overflow, and whether harvested water is intended for storage or recharge.
Standard / planning reference
Treatment, storage, and recharge arrangement meets local requirements and intended use
Evidence to collect: Approved rainwater harvesting schematic and commissioning check
Risk if skipped: Poorly managed roof runoff can introduce debris and contaminants into storage or the recharge system.
Plumbing planning notes
Use this checklist to coordinate decisions and collect evidence, not as plumbing instructions or an engineering specification. Confirm materials, dimensions, test methods, and acceptance values for the actual project.
Review sleeve locations against structural drawings and plumbing layouts before concrete is placed.
Keep test results, inspection notes, and approvals with the project records before covering pipework.
Coordinate pipe gradients, traps, penetrations, and waterproofing details with the project professionals.
Planning aid only, not plumbing, structural, or engineering advice. Plumbing design, pressure testing, structural penetrations, waterproofing, and rainwater systems must be reviewed and verified by qualified professionals under applicable current standards and local requirements.